Zatonskaya CHPP 2х220 MW (Ufa, Bashkortostan)
The Zatonskaya CHPP was put in operation in Ufa. The Head of the Republic of Bashkortostan Rustem Khamitov took part in the power plant inauguration.
The new power plant comprises two power generating units with a total electric capacity of 440 MW and thermal capacity of 290 Gcal/h. The CHPP is equipped with modern high-efficiency CHP equipment manufactured in Russia. Natural gas will be used here as the prime fuel.
The new CHPP will decrease the electric power deficit in the Ufa electric generation system. The power station will be the major thermal power source for the prospective construction area of Ufa. No electric power stations this big has been put into operation since the 1970s. The amount of investment into the project exceeded 22 billion rubles.
This station completed the CDA program for Inter RAO-UES.
For this project, CuprAl Bridge manufactured and supplied isolated phase buses of different types:
- TENE-20-8000-300 NF1,
- TENE-10-6000-250 NF1,
- TENE-20-1600-560 NF1,
- ShZK 1.2-2000-81 N3,
- TZKR-1-2000-128 NF1,
- TZKR-1-1600 NF1.
The overall total of the equipment supplied is 1,265 meters.
March 13, 2018